STAYING A STEP AHEAD IN THE GAME
Naveen Kumar
Construction Manager (Electrical), PT&D IC
Naveen Kumar, presently at the KRCL Package 3 Project, has been associated with PT&D since 2007, right from his GET days and has been a part of several successful project deliveries. “There are several factors that contribute to achieving a milestone but planning ahead has always given us the decisive edge and in the pandemic environment, we have successfully closed in on many fronts largely by being proactive.”
“This is a one-of-its-kind project with the task of building critical power infrastructure at an altitude of over 980 m MSL where every move of ours has to be precise,” shares Naveen. With four substations aligned inside the tunnel and a 33 kV HV cable laying over the Chenab bridge, the highest railway bridge in the world, Naveen and team has a tall list of deliverables. “We took stock of the situation and listed out the tasks that had to be closed immediately such as the hill cutting works that was not in our scope but key to establishing base for the substations.” The team safely executed close to 5000 cum of hill cutting through their own resources that included rock bolting and soil protection works in a challenging terrain that was a new learning for them.
For Naveen, appreciating the larger picture was critical in an highly complex project as KRCL.
“We all have our targets but then there is an overlapping portion involving other stakeholders that has to be done seamlessly to achieve the milestones,” he points out. Some smart thinking enabled the team as well as the external stakeholders to be on the same platform through a common group where daily work progress and issues are shared. “It is a real-time update and the team’s collective effort has ensured that we have plugged the gaps based on priorities.”
Hailing from Hisar in Haryana, Naveen’s family includes his wife, Shweta Sood, who is working with Allianz Insurance as an Accounts Payable and two sons, Pranay, who is six years old and Vivaan, who is three and a half years old. Playing cricket, listening to music, and watching movies are Naveen’s hobbies but he admits, “on a weekend, a day well spent with family gives utmost relaxation.”
Naveen acknowledges his Project Manager’s support. “He has played a vital role, trusting my capabilities that has empowered me to take timely decisions to help complete several key deliverables. The raft of the GIS building is in place, and we are on track to complete the balance of works by December 2022,” he declares with a steely look in his eyes.
L&T HAS TAUGHT ME HOW TO FACE CHALLENGES AND EXTREME PRESSURE!
Tanmay Dwivedi
Senior Engineer (ELECTRICAL), PT&D IC
“Once we have taken up a project, it is our responsibility to complete it in time,” says Tanmay Dwivedi seriously from his complex KRCL project Packages T3 and T5 where he is the Planning Manager. “This is one-of-a-kind project,” he shares, “so we got cracking right away setting our immediate milestones to get our drawings approved for GFC. There is a lot of electrical, mechanical, and instrumentation equipment to be installed at appropriate places in the tunnels so we surveyed all the tunnels and backed by the EDRC team at Chennai, we all worked night and day to come up with the best possible solutions.”
“Our project monitoring plan is simple,” he says with a deceptive lightness, “with a precise micro plan prepared from day one. We have set daily goals for the execution team and all the site engineers have been instructed in submit daily work progress along with geo-tagged photos in a WhatsApp group. We have engaged different subcontractors and divided the work fronts into different sections to monitor and accelerate progress parallelly across fronts more effectively.” Redeployment of labour after the complete lockdown was a serious challenge, but as Tanmay remarks, “we built trust and assured safety of all.” Crucially, Tanmay and team did not allow COVID-19 to overcome the project by strictly following all the SOPs. “In fact, during this time we got more time with the client to finalize our designs and resolve land and other disputes.”
Digitalization is leading the way for the team and apart from conducting online meetings, the team uses the safety related SHIELD App, the Quality App, and the ALIGN tool to monitor project progress regularly. At the end of each day, progress updates are entered into the micro plan and a comparison made with the baseline schedule for course corrections, if any. “We keep track of workmen safety, the quality of works, project progress and more by remaining physically distant but digitally connected,” he smiles.
Having joined L&T as a GET in 2017, Tanmay is at his 3rd project after earlier stints at the IPDS Kanpur project as Site Engineer and later at the Saubhagya-LKM project, initially as Planning Assistant and later as Planning Engineer. “I joined the KRCL project in November 2020,” he affirms. Hailing from Kanpur in Uttar Pradesh, Tanmay is still single and when asked about his life partner, he grins mischievously, saying, “She must be eating pizza somewhere!” He loves playing cricket and badminton.
“Our Project Manager has always shown the way and motivated us to achieve our project targets while L&T has taught us how to face extreme pressure and challenges and that there is no compromise for quality work,” he signs off on a high.
THE IMPORTANCE OF MAINTAINING
GOOD RELATIONS
“We are executing a terrific, challenging and iconic railway tunnelling electrification project for the Konkan Railway Corporation Limited in the Jammu & Kashmir region that will play a vital role in the development of our nation,” begins a proud Marripudi Gopi, who is presently engaged as Project Accountant for the KRCL Packages T3 & T5 at Reasi and PDS Packages T1, T2, T8, T9 and T10 at Katra, both in J&K. “Considering its critical geographic location, we have developed several pieces of infrastructure around the project location in very hilly terrains for hassle free construction activity,” he shares. The team has put up the project office, stores, staff residencies, guest houses and the labour habitat. “Thanks to these, the project has accomplished a big milestone within a short timeline as per the contract,” he emphasizes.
The shock and disruptions caused by COVID-19 have revealed vulnerabilities in several organizations, but Gopi believes that L&T has faced the challenges with greater resilience. “Our efforts at digital transformation have helped us recover from these unexpected shocks quicker than others. At the same time, by mobilizing the adequate number of skilled workforce and technical experts, we have successfully fast forwarded our project.” Gopi feels that a professional approach helps in these unprecedent times. “It is important to understand an internal or external customer’s point of view, assess their needs, evolve a solution and seek support depending on the specific needs but, most importantly, maintain good relationships,” he advises.
To keep people safe at site, Gopi and team have ensured that all staff and workmen have been vaccinated at least one dose, arranged oxygen concentrators, tied up with local hospitals and regularly sanitize all premises. “A Face Reading Machine captures the attendance of both employees and workmen and every project employee has a GPS device that identifies their physical presence at site for security purposes considering the location and the terrain.”
Gopi is from Venkatapalem in the Guntur district of Andhra Pradesh and is married to Usha, a homemaker. The couple are blessed with two children, son, Siva, and daughter, Nandini. Their births are Gopi’s life’s most cherished moments. “I like to play cricket and watch movies but find it hard to follow them at the project site,” he says a trifle wistfully.
“Recognition and appreciation for successful events from all levels of hierarchy motivates one to achieve more and more in the form of significant collections or even, on time project completion,” says Gopi in conclusion. “Of course, motivation to make bigger contributions fills me with pride for being part of this multinational conglomerate.”
AN ALL-ROUNDER PROVING HIS EFFICIENCY
Senthil Kumar G
Senior Construction Manager (Civil), PT&D IC
Senthil Kumar G is a bit of an all-rounder. “I have been associated with cement plants, nuclear power plants, refineries, glass factories, hospitals, spinning mills, residential buildings, substations, EWL/ TLTRC and pole factories,” perhaps more than a lifetime’s portfolio for many. At his current station, the 132 kV GIS substation and EHV cabling for Line 7, MMRDA in Mumbai, Senthil is hard at work to complete the transformer and equipment foundations, the terrace slab of the substation, provide access to GIS installation in 110 kV and 33/25kV and EHV cable laying.
With Mumbai remaining a hot zone for long and workmen from their normal catchment areas of Jharkhand, UP and MP unwilling to travel, Senthil and team mechanized the civil works. “We mobilized the tower crane and since we were attempting it for the first time in Mumbai, we consulted other contractors who were already executing this type of a job and mobilized resources that helped us big time to achieve our target in time.” His is a winning smile for in the process, they saved 2.5 months in civil structural and finishing works
“Our project basically involves three different types of works: construction of the substation, equipment foundation, RC bridge, boundary wall, access roads, EHV cabling (3 km) and auxiliary substations at 13 different locations of metro stations from Andheri to Dahisar,” he explains. “We have therefore created different sections headed by a Section In-charge according to the nature of the job and location which has helped in execution and monitoring progress.”
Protecting the existing trees was another big challenge for the team as the authorities had prohibited any tree cutting. “Adequate care was taken when designing the site layout to protect the trees,” Senthil nods. The Opticvyu cam installed at site helps the team monitor and record activities round the clock while the CCTVs ensure security and progress monitoring.
Hailing from Chengalpattu, Tamil Nadu, Senthil’s life partner, Dr Renuga, who is a Siddha Doctor running a small medical consultancy apart from looking after their home and their twin daughters, Maha Lakshmi, who is doing her final year B. Tech in Bio Technology and Vijaya Lakshmi, who is into her 3rd year in MBBS.
Unsurprisingly, all Senthil’s life memorable moments feature achievements at the various sites he has worked; be it achieving a 7 days’ slab cycle at the Mughal Gardens project or establishing 4 factories at 4 different locations in UP in 2018 or even winning the British Safety Council, ROSPA, and Quality awards in Tata Power in 2012. “I am proud working for India’s No 1 construction company and enjoy the opportunities to prove my efficiency and expertise,” he signs proudly.
IT’S ALL ABOUT ACHIEVING A PERFECT SYNC
Rahul Dadarao Harnawal
Construction Manager (Electrical), PT&D IC
Executing extra high voltage substations is a complex task and all about achieving a perfect sync between the civil, mechanical, and electrical works, a task that Rahul Dadarao Harnawal, Construction Manager (Electrical), has been excelling at over the years. “It was a little different here being PT&D’s first substation for Mumbai Metro involving the construction and commissioning of a 110/33–25 kV receiving substation and 13 auxiliary substations.”
With Mumbai badly affected by the pandemic, execution was always tough, mentions Rahul. “We diligently made inroads with special permissions and closed in on some of the most challenging milestones such as laying the 148 Km HT cable with the help of the traffic police and local authorities.” The heart of the project was the construction of the power centre over a 3600 sqm plot that posed the team multiple challenges.
“As there was an existing 6m wide storm water drain running through the plot and a 14.5m concrete bridge connecting the two sides of the land area, we came up with a sustainable construction scheme, reworking the foundation design by increasing the depth and size of the rafts to secure the green zone in and around the plot.”
“Arriving at on-site improvisations was always a team game with every player coming up with unique ideas,” reveals Rahul. “Every time we hit a bottleneck the team sat together to crack suitable solutions. Like when we had a mobility issue due to space constraint, we implemented a temporary bridge and erected a 20m high tower crane with a 35m boom reach which quickened completion of works with lesser manpower, ensuring safety and quality within a 3‑month period.”
24th May 2021 was a red-lettered day for Rahul and his team as the substation was charged. “This milestone facilitated the overhead electrification of the line and subsequent trial runs. We have gone a step further to synchronize the auxiliary substations thereby adding one more powerful benchmark to PT&D’s list of achievements.”
A native of Solapur in Maharashtra, Rahul is delighted for having contributed to the construction of iconic projects in his home state. “My wife, Sanchita, is a banking professional, who keenly follows infrastructure development as it has a direct bearing on the economy. We have lively discussions on how projects transform lives and L&T’s role in nation building.”
Young Siddhant Agrawal’s life’s most memorable moment was when he was appreciated by his client, MMRDA, for their work at the Mumbai Metro Line 7 project, during the pandemic. “One of our biggest milestones was to achieve ‘Zero COVID-19 positivity’ among the workmen,” he shares excitedly. “The client’s appreciation was great as was the appreciation certificate we received for store management. Our other important milestone was to successfully charge the RSS during the difficult pandemic time.”
This recognition are the high points in Siddhant’s young career that began in 2015 when he joined L&T as a GCT, and he is presently at his 4th project. At his first RAPP (RJ) to Sujapur (MP) transmission line project, a fast-tracked one for Sterlite, he learnt the functioning of stores and the accounting/admin/time office works. At his second, the ‘Waroora to Parli’ transmission line project, “I was given overall responsibility that moulded me for the future. I singlehandedly handled ROW, administration and time office works,” he says proudly. Next, he speedily demobilized the Solapur to Parli site in some 4 months, clearing all issues with no material or issues pending and after a short deputation at the Nagpur Cluster Office, joined the Mumbai Metro site in 2019.
With Mumbai being perhaps the worst affected zone, retaining labour was their primary concern, succeeding to hold some 100 in the labour camp. “Being from a service department, I provided immediate support to fulfil the requirements of the execution team and this support from behind is equally important for on time execution,” he remarks. “A key aspect to monitor the progress has been communication and maintaining it continuously with both employees and workmen. In fact, I have been in touch with every workman to understand and try to resolve their issues and pain points.”
While digital solutions have given the entire project team a huge advantage, through various training programmes at site and BU levels, Siddhant has learnt the procedures of the execution team. “My seniors and colleagues have totally guided and supported me. Without their guidance it would not have been possible to achieve our milestones,” he says earnestly.
Born and brought up in Mumbai, Siddhant says, “I like to play outdoor games like cricket, badminton and video games as well but being posted at project site, it is difficult to take out time for them. I try to follow my hobbies on holidays,” he grins.
“I am proud by the way L&T has supported all the employees and workmen, and how we have all stood together to face this pandemic,” he concludes, proud of his association.
INNOVATIVE CONSTRUCTION METHODS TO CATCH UP TIME
Sheik Oli Abdul Azeez
Construction Manager (Civil), PT&D IC
With a name like Sheik Oli Abdul Azeez, one would expect him to be working somewhere in the Middle East and he is, at the SEWA — Layyah 220/132 kV Substation project in Sharjah, UAE. In fact, since joining L&T in 2017, Sheik has been involved in two other PT&D projects, both in Dubai — the DEWA — 132/11 kV Qanat Substation and the DEWA — 132/11 kV Garhoud Substation projects. “Our handover is in two stages, the first by April 2021 for the 132 kV System and the rest by October 2021,” he explains, “and our aim, as per schedule, was to complete all the civil works before April and our 1st Energization Date. Although we lost some man-days, progress and missed some targets due to the pandemic, we still achieved our first milestone 4 days ahead of schedule,” he shares with a happy, winning smile.
Preparing, following, monitoring micro schedules, arranging for additional resources within their ACE limit and conducting daily meetings to review progress were how they managed to stay ahead of the crisis. Sheik is impressed by what he and his team achieved by implementing innovative construction methods to reduce the execution time for each activity. He mentions the introduction of a temperature control system for mass foundation concrete and 7‑day periods for curing, verified with lab results & readings and conducting a GPR survey with a specialized agency to identify the existing UG services to lay a new foundation route along the GIB structures. “We adopted a simple pile on raft construction method by treating only the waterproofing membranes instead of the common blockwork protection method with acceptance from client,” he points out.
“Ours is a motivated workforce with rewards and recognition for performers and we have skilled teams identified and deputed for critical activities,” he remarks. “Multiple activities are taken up parallelly to reduce execution time, both internally and externally by appointing additional vendor teams for the finishing works.” Monitoring daily targets, measuring productivity, conducting frequent site inspections, and maintaining transparent communication within the team are helping them to stay true to their course.
Sheik is thankful to his Project Manager, Mr. V Oscar, and Cluster Managers, Mr. Sooraj & Mr. Chayan for their continuous motivation and to his project team of Sabuj, Jayakrishnan, Vignesh, Mahendran, Rajendra & the front-end office team for being his backbone to achieve their milestones and targets.
From Chennai in Tamil Nadu, Sheik is married to Benazir, a homemaker, and the apple of their eyes is their 5‑year-old son, Muhammad Ihab, who’s birth has been Sheik’s most memorable moment. “I love to listen to music, watch cricket, movies, play table tennis, exercise and walk during weekends and on holidays,” he smiles.
AN ARTIST AT HEART AND AT WORK
Mohd Momin
Construction Manager (ELECTRICAL), PT&D IC
One of Mohd Momin’s favourite hobbies is to read Urdu poetry and that is the same sensibility and sensitivity that he brings to his work. Presently working at the Layyah 220/132kV Substation project in Sharjah, UAE, Mohd is playing his second innings at L&T having first joined as a GET in 2006, worked for 6 years in various capacities, left in 2012 and then returned to the ranks in September 2017 as Planning Manager with PT&D UAE at the 33/11kV Substation project at Al Ain, Abu Dhabi, UAE.
Mohd’s immediate milestones at site were addressed by identifying detailed activities of all work sequences and focusing on independent activities that could be completed during the slowdown in the construction phase like completing engineering details through virtual meetings, convincing the client, and conducting online FATs of major equipment. “Of course, we had several challenges post the relaxation of the pandemic restrictions,” he says grimly. “Supply chains of the material market were disturbed leading to less availability of consumables locally, less availability of labour and subcontractors for works and disruption in the production of long lead items especially from overseas.”
To address these issues, the team started to stock consumables in bulk wherever available locally, which could be required even after six months and increased labour productivity by motivating and ensuring them complete facilities during the pandemic like regular health check-ups, extra buses for maintaining social distance, etc.
“We divided the workmen into groups during working hours at site and during their stay at the labour camp,” he explains. “If any workman showed symptoms, he was immediately isolated. Each group had two gangs of 8 workmen each, accommodating all cadres of workmen. The activities in the critical path were continuously engaged with different gangs and shifts. Most of the subcontractor teams were asked to come at different times like the scaffolding team started activities at 2 am.”
Mohd recognizes the huge benefits of adopting digital solutions. “All meetings and FATs were conducted online, saving time. We used the ALIGN App to monitor the project and OPTICVYU time lapse camera for real time project updates,” he shares. “As progress was monitored online, delay in any activity with respect to baseline schedule was immediately highlighted in weekly progress meetings and actions were taken accordingly.”
Perhaps, Mohd’s liking for Urdu poetry can also be traced to his native place of Lucknow (Uttar Pradesh). His wife, Hera Khwaja is a homemaker, and they are blessed with a daughter, Aliza Quamar. Apart from poetry, Mohd loves to watch TV and some of his best moments are watching movies with his family.
SMARTER YOU WORK, GREATER YOUR ACHIEVEMENT
Mathan Subramani
Assistant Manager (Accounts & Admin), PT&D IC
Having joined L&T in 2005 as a GCT, Mathan Subramani is presently on his second overseas assignment at the Layyah 220/132kV Substation project in Sharjah, UAE that involves design, manufacture, supply, installation, testing & commissioning.
With positive COVID cases rising at site, the challenge for Mathan and team was to separate the infected from the regular camp and help them recover to resume work. “While we strictly adhered to the stipulations imposed by the client and the local authorities regarding manpower movement, resource mobilization at site was a major challenge,” he shakes his head. “Due to the lockdown, it was difficult to obtain Federal Authority Approvals / Municipal permits on import goods making it difficult for us to bring in imported consignments.” They also had to deal with an agitated workforce, many of whom wanted to return to their native places.
On the execution front, work was progressing as teams were working in batches with defined time schedules to fulfil the statutory norms issued by the local authorities. “The client supported us to a great extent,” nods Mathan, “and our good rapport and relations with the government authorities helped to get our clearances on time.” The team carried out weekly inspections of the workmen camp and awareness was incorporated as a part of the mission to be achieved.
Apart from strictly following all the pandemic protocols effectively to ensure a healthy environment, what helped improve the sentiments at site was vaccinating the entire workforce. “This boosted workman confidence, and we were more successful thereafter to motivate them to perform better,” smiles Mathan.
Suggestions, motivation, regular feedback from the Project Manager, following the frequent guidelines & updates from the Cluster / Area Offices & the pandemic team and round-the-clock vigilance made the things easier.
“The present trend is for everyone to have smart phones, so we educated the workmen to use mobile Apps like SEHA/DHA to book appointments for vaccination & ALHOSN to get their results as well as track their medical history,” informs Mathan. Regular site meetings, cluster reviews, training events were all conducted virtually, material movement was tracked and recorded through CCTVs, LMV vehicles tracked through RFIDs while site progress was monitored through OPTIC.
Hailing from Tirunelveli in Tamil Nadu, Mathan is married to Gomathi, a homemaker, and they are blessed with two daughters, Aishwarya and Madhu Bharathi. “As for my hobbies, I love to play badminton with my kids especially in the mornings,” he laughs, “and welcoming my family at the Dubai Airport for their first international trip was a memorable moment.”
About work, he says, “the smarter you perform, the greater will be your achievement!”
A PENCHANT FOR TAKING UP CHALLENGES ACROSS NEW HORIZONS
Shelbbyn Michael Raj, Project Control Manager, at the Rehabilitation & Upgradation of Electricity Network of Hassi Berkine Bassin area near Algeria continues to do what he is best at. “All through my career, I have handled core power infrastructure projects largely in the Middle East. After joining L&T, my international stint continues, of course, in a new region with the larger onus to deliver a composite power network that is more like a hot line stringing.”
We are called the ‘Desert Warriors’ for very good reason, he mentions with a grin. “A large span of our job is right across the Sahara Desert to revamp a 220 kV power station in live conditions across 19 locations comprising 8 substations and 11 Central Processing Facilities.” Even planning movement from one work location to another is not easy. “We have restrictions other than the pandemic-imposed lockdowns as the region is very sensitive and our every move is under security cover,” Shelbbyn mentions with a serious look. “Then there is the challenge of working and living within a bio-bubble with our first point of resource access being 400 km away. However, thanks to our meticulous planning, we have largely been on track in a job of this nature which is a trailblazer project for PT&D.”
For someone who has successfully executed power infrastructure project across oil and gas industries, Shelbbyn has been up to the task in the present assignment. “The existing network supplies power to the oil and gas industries around this region and any power disruption would have directly impacted their operations.
One of the first priorities we lined up was the decomposition activities along with the sequencing. These are basics in project execution but here, we had to consider the live revamp without a shutdown window. Resources had to be deftly handled as we had to balance the works depending on the criticality and timelines. What worked for us was a combination of many factors with technology giving the edge.” For the first time in PT&D, Shelbbyn is proud that they made use of mobile substations. “It’s a plug and play station that comes at a price but then gets the work done which is what really matters.”
Shelbbyn owes a lot to his wife, Seethalakshmi, who opted over her career to nurture their daughter, Riya, who is seven years old. “She gave up her banking job but there are no regrets as she is instrumental in shaping my daughter’s aspirations.”
MAKING A CONSCIENTIOUS SHIFT
At L&T, opportunities come in the form of challenges and for Venkateswarlu Aitha, Senior Manager, (Electrical), the shift from domestic to international projects has been action packed. “Over the last 14 years, I have handled a range of projects across the distribution sector involving air and gas insulated substations which includes new-age technologies like Statcom and Metro power infrastructure. Moving from an engineering and project management profile to lead a design team to evolve field engineering solutions at the Rehabilitation and Upgradation of the Electricity Grid Berkine Bassin in Algeria has been a big break for me.”
This project is all about breaking new grounds and for Venkateswarlu, converting challenges into opportunities began with digital tools. “A project of this stature, if bagged a few years ago would have been tough to execute but with new-age applications like 3D scanning, we are able to do the seemingly impossible, to work out a load transfer plan in live conditions to save close to 55 days of construction time.” Elaborating on the scheme, Venkateswarlu shares, “with a conventional approach, it is mandatory to upgrade the existing power infrastructure through a shutdown window, but we were able to collect ‘as-built information’ through LiDAR processing based on which the workplan was finalised.”
The biggest gain through this digital mode was to get the client’s endorsement, shares an elated Venkateswarlu. “Proposals for all the 19 substations including the 11 central processing facilities details were reviewed online by the client thereby reducing the approval cycle time to 7 days from the existing 21 days. Going further, we bridged the pandemic restrictions by routing the Factory Acceptance Tests through MS Teams involving the OEMs and clients wherever physical interface was not possible.”
On-ground improvisations was another factor that contributed to completing the milestones. “EHV cable termination activities are usually carried out either by OEM or OEM-certified jointers,” he remarks. “However, as the respective OEMs regretted about deputing their personnel, we sourced technically qualified locals to close in on such critical activities with a fair bit of orientation.” Keeping tab on activities, spread across the Sahara Desert, was another challenge but the ‘Align’ tool provided the team notifications in real time. “Most of our internal progress reporting was in line to enable approved progress measurements from the client’s end.”
Back home in Chennai, it is the same digital platform that connects Venkateswarlu with his family. “My wife Sandhya along with my children, Saharsh and Sashreek ensure that distance never matters as they relate all their updates with my mother chipping in with her occasional advice, making me feel at home so far away from home.”
From a slow start to steady progress is what Gadmsetty Venkateswarlu, Section & Wayleave In-charge has achieved at the 275 kV Medamit to Lawas Town Transmission Line Project. “Our tower alignment is largely through hilly terrains and with the region receiving seasonal rainfall of close to 7 months a year, establishing access to work spots was our primary challenge. Thanks to technology, value engineering and mechanization, we have been able to make timely breakthroughs to surge ahead.”
In the first six months, the team completed 50 foundations while the next 50 were achieved in just 3 months’ time. “This is my second transmission line project in Malaysia after the landmark 500 kV Double Circuit Transmission Line from Yong Peng East Substation to Point ‘A’ (Mukim Jabi, Daerah Segamat),” informs Venkateswarlu, “but the conditions are largely similar with the terrain presenting similar challenges. It is crucial to quickly establish the RoW as it paves the way for taking up core works.” At site, Venkateswarlu and team worked on a time-tested ploy of splitting the work force into two units, “this way, we were able to zone in on work fronts and balance the flow of progress.”
Having executed several projects in the Middle East and Africa, Venkateswarlu, is certainly aware of the importance of technological improvisations. “Minor customizations enabled the team to achieve significant breakthroughs like fitting the excavator with a modified concrete bucket which facilitated pouring of concrete especially in hilly terrains where the conventional mixer machine was not feasible for operations.” Likewise, “the team made good use of the local infrastructure and manpower to do the base works with the required orientation,” highlights Venkateswarlu.
Sarawak presented a unique challenge. “Though a part of Malaysia, this region is more like an independent country with its own set of rules and regulations with the pandemic making travel regulations even tougher.” A mixed macro-micro approach drawing on L&T’s project management expertise enabled Venkateswarlu, and team set the course.
Hailing from Kalasapadu in Andhra Pradesh, Venkateswarlu’s family includes his wife Usha Rani, who is a senior software engineer, and daughters, Manvitha and Jaashwika. A break from work means connecting with family and enjoying a session of his favourite stand-up comedy. “It’s my way of relaxation that works wonders for me,” he signs off on a happy note.
Even as the world reeled under the impact of the pandemic, there were many hardy L&T‑ites like Vempalli Aseef fighting it out. At his Medamit to Lawas Town 275kV transmission line project in Sarawak, Malaysia, he plays the dual role of Section In-charge and Engineering Coordinator and is most willing to make sacrifices to push progress. “We effectively utilized the lockdown period by conducting virtual internal meetings with all stakeholders to develop a micro level plan for immediate milestones,” he says. “We identified bottlenecks and addressed them by assigning responsibilities and explored opportunities for mechanization wherever possible.”
Aseef loves to adapt to new technologies reflected in his smart work at site by dividing the civil works into sub works, engaging different groups for different activities like civil works involving access road preparation, platform preparation, logistics (material shifting), foundation works, finishing works and such like. “Since all these works are under one subcontractor, the normal practice would have been for the same team to do them all but by dividing the work we were able to push forward across several fronts,” explains Aseef. In addition, they identified local companies with the potential to mobilize large amount of machinery, recruit local workers and trained the available local workmen by providing technical and supervisory support.
Of course, Aseef and his team had to face several challenges like following the new SOPs and face prolonged restrictions on travel from other states and countries that resulted in a scarcity of skilled resources. “New subcontractors were unwilling to work at our remotely located project with many travel restrictions to reach the project site.” Though stressed, Aseef and team managed to overcome their challenges using a nice mix of mechanization, digitalization, and effective use of available local resources.
Aseef is happy about two smart introductions that gave them several advantages. “We introduced larger mixer machines for concreting, saved up to 5–6 hours with lesser manpower and even overcame the issue of scarce skilled manpower,” he says, mentioning the introduction of dozers to prepare access roads and platforms instead of excavators that proved useful for cutting & pushing huge quantities of soil in a short span of time. “We monitor project progress through drones and issue work permits through the SHIELD App,” he remarks, “and taking advantage of our time difference, we are two and a half hours ahead of India, we interacted with EDRC daily to complete the engineering,” he smiles.
Presently, at his 4th project with L&T, Aseef hails from Piler, in the Chittoor District of Andhra Pradesh, is married to Shabnam, a homemaker, and they are blessed with a daughter, Aaliya.
SEEKING LOCAL SOLUTIONS TO DRIVE PROGRESS
Nikhil Mundada
Assistant Construction Manager (Elec), PT&D IC
“Words have the power to light up minds, provide the right kind of motivation and when shared by the leadership, they become almost a mantra to propel business forward,” says, Nikhil Mundada, who dons multiple roles as planning manager, project scheduler and procurement support at the 275 kV Medamit to Lawas Town Double Circuit Transmission line. “I vividly recall the last townhall meeting where our IC Head mentioned that as the Columbus of L&T, the Sun should never set on PT&D’s empire. For me, those words are memorable for they clearly capture the intensity with which the company wants to grow.”
For Nikhil, the last decade at L&T has been very successful. Joining as a PGET in 2011, he has handled a mix of PT&D projects beginning with the landmark Hyderabad Metro Rail. Later, he shifted base to Malaysia at the Samalaju‑B Substation project as a Primavera expert & Planning Manager, provided project tendering support for the ASEAN Cluster‑1 and is now at Lawas Town, with a range of deliverables. “Things initially did not go as per plan due to the pandemic and the hard work began with the rescheduling of the execution schemes based on local issues,” he says ruefully.
With the Malaysian borders closed, mobilization of overseas skilled workmen took a beating for the team. “All our efforts were in vain, and we had to look for inexperienced locals; also, for teams from Thailand but with limited options,” he shakes his head. “Similarly, material transportation became increasingly difficult due to restrictions at the state border. The only way out for us at this juncture was to bank on the inexperienced locals.” The team therefore took the risk by deputing a team of engineers to train the locals starting with the basics. “On field, the tower foundation team was a mix of experienced and unskilled workmen which gave balance and direction to complete the task across the alignment spanning close to 131 Km.”
While pushing hard to make progress, support from the client and vendors helped their cause immensely. “The client ensured smooth cashflow with timely payments while our vendors supported execution through remote FATs saving us cost and time. We not only used drones to capture site photographs, but also trained our safety officer to use them for site inspections.”
Nikhil fondly mentions his knowledge sharing sessions with his wife, Preethi, who is a civil engineer. “She chose home making as her career when I moved to Malaysia in 2016 but we discuss on many project issues and it’s always nice that my work is acknowledged from her end.” The couple is blessed with a daughter, Riddhi, who is the joy of their lives.