GETTING TBMS UP AND DIGGING!

Getting TBMs up and digging!

TBM shield being lifted at Mumbai Metro Package 03 UG 01

With the rising demand for underground infrastructure primarily due to space constraints, the role of TBMs or Tunnel Boring Machines are assuming greater relevance to excavate tunnels, across various types of soil strata. Since India does not presently manufacture TBMs, all those in use are imported. Of late, L&T has been employing several TBMs across project sites having launched a few recently at the metro rail projects in Mumbai, Bengaluru, and Ahmedabad, in several cases without much help from the OEMs.

At the Mumbai Coastal Road Project (MCRP), Sandeep Singh, Project Director of Package 4 has an 80 M long TBM with a 12.19 M diameter, weighing 2,300 T with an installed capacity of 7,280 kW to assemble. “It is the largest in the country,” he says seriously, “specially procured to excavate in deep overburden through a compound stratum of basalt, breccia and shale for which it is equipped with a mixed cutter head with eight spokes and eight panels to bore in the complicated strata for a long distance.” Assembling such a complex piece of equipment is Sandeep’s biggest challenge.

Certainly, the process of assembling, launching, and putting a TBM to work calls for knowledge, precision, and high safety standards, recognizing which L&T’s Tunnelling Excellence Academy is training and preparing tunnelling experts.

Safely transporting a TBM to site

Launching any TBM takes weeks of planning and preparation but the mandatory first step is for the OEM to confirm that the TBM has successfully undergone a Factory Acceptance Test (FAT) before shipping it. “This is where the fun starts,” grins Michael William Sanderson, Head – EHS, Heavy Civil IC. “Once the TBM arrives in India, it has to be safely transported to the project site and our safety obligations begin as soon as the TBM is off loaded onto a trailer.”
The MCRP TBM when dismantled filled as many as 17 trailer trucks. Right from leaving the dock yard, the EHS team must be on their toes. Transporting the TBM in urban environments is particularly strenuous: carrying the cutter head (with varying diameters), the shield and supporting gantries which were assembled at the factory and then disassembled for transporting.

En route, the risks are enormous for the trucks and their escorts are regularly checked and verified at various check posts. “We must consider the emergency vehicles accompanying the TBM, notify the police and fire brigade about our routes and timing but public safety is paramount,” Michael emphasizes.

TBM 1 (AVNI) commissioned and TBM 2 (LAVI) assembling in progress

Safely building it at site

Once safely unloaded at site, the team must put their minds and muscle to building the TBM. The sequence is crucial, and the shaft determines the order of reassembly. Some L&T projects have vertical shafts that only allow the shield to be lowered followed by the cutter head by cranes, carefully chosen considering their lifting capacity and capability to lower all the TBM components above the shaft. “The Mumbai Metro Line 3 used a 1000 T crane and they had to divert traffic for nearly 3 months in an extremely people and vehicle dense location to complete the task,” remarks Michael with a roll of his eyes.

G Divakar135x175 copy

Every day brings new activities and fresh challenges.

G Divakar

EHS Compliance Head, HCI IC.

Through all this, Safety remains the key consideration. Understanding the risk of every activity is crucial for the team and then to plan and work together on every aspect from design, P&M, EHS, execution. Safety is top priority for the Tunnel Manager too because any load failures can be catastrophic. “Every day brings new activities and fresh challenges,” chips in G Divakar, EHS Compliance Head, Heavy Civil IC, who has been in the thick of TBM action at several Heavy Civil sites.

No external support; only internal strength

Normally, specialized TBM erection teams from the OEM lead the process of assembly. In the new normal, with overseas teams unable to travel, it has been left to the L&T teams to take up the onus of assembly with only ‘virtual’ help from OEM engineers. Project Manager, Sridharan Srinivasan, RT 03 Bangalore Metro project, who spearheaded the successful launch of two TBMs at his site shares, “Collectively, we had very little experience in TBM commissioning and zero experience in this type of Slurry TBMs but we took it on as a challenge and our young team of some young and bright engineers were able to pull it off!”

TBM 1 (AVNI) auxillary shield tandem lifting & lowering in progress

The challenge for Project Manager, Vivek Maruti Pai at the other Bangalore Metro package RT 02 project was to assemble and operate Slurry TBMs to suit Bangalore’s geological conditions, an entirely new proposition. To add to their troubles, the excavation of the shaft was becoming extremely difficult due to certain geological constraints. “We were forced to use an umbilical system that is more complicated both in assembly and operation, but we succeeded.” Vivek is both exultant and relieved.

Ahmedabad Metro Tunnel

All in it together

Although there are experts, everyone involved in the TBM assembly must take specific tunnel inductions as different tunnels pose different hazards and safety risks. An EHS Tunnel personnel guide lays down the EHS systems to ensure a safe assembly. All likely hazards and risk must be prior identified and controlled, captured in risk assessment and method statements that are submitted to the client for approval before starting the process.

Launch of TBM Avni at BMRCL RT 02

Lowering after the assembly

Once the TBM shield is built, the gantries are lowered. Each gantry has a specific function and has been designed specifically with safety in mind. As the build continues, every part of the TBM must be tested, under a Permit. “Here, the left hand must know what the right is doing,” smiles Michael. “Accidents occur during the assembling and commissioning stage as the machines become very confined so wearing PPE is a must especially protection for the eyes during welding and handling of pressurised hoses,” he stresses. Fire protection systems and personnel must remain on red alert till the build is complete. Work at height needs to be considered too when assembling the shield and the gantries in the shaft area. “The shield is round and if you miss your step walking on the top, you can land several meters below so fall protection is important,” points out Divakar. Gantries require handrails as walkways over 1 m as anyone can fall, because the existing tunnel lining is used for protection of falls during tunnelling. Therefore, only authorised persons are allowed into the shaft to ensure safety.

Michael William Sanderson135x175

Tunnellers are a rare breed. They work all around the world, but team spirit is always the same everywhere you go: Safety runs in their blood like tunnelling.

Michael William Sanderson

Head – EHS, HCI IC

Putting them all together

Gradually the TBM takes shape and every component must function as it is intended to. Tunnel experts use temporary umbilical cords to move the machine. The sight of the cutter head rotating for the first time is certainly exciting but only privy to the Tunnel team with all safety systems in place with a specific pass system called a ‘Tally’. “Everyone must Tally in and Tally Out of the shaft,” points out Michael, mentioning the need for a self-rescuer in the shaft area once the TBM starts boring. Gas is measured too for unwanted pockets and, oxygen levels checked. Prior to boring a tunnel, soil investigations are conducted to understand the lay of the land, though risks still exist especially in the form of undetected hazards such as gas or water, so every risk has to be considered to protect workmen and the public.

Assembling a TBM requires meticulous planning, careful preparation, clearly defined methodology, perfect teamwork, and fastidious adherence to safety protocols. “It is asking for a lot,” laughs Michael, but then assembling a TBM does take a lot out of the team. “Tunnellers are a rare breed. They work all around the world, but team spirit is always the same everywhere you go: Safety runs in their blood like tunnelling.”

Lifting of TBM backup gantry at Mumbai Costal Road project,
package-04

Read Previous

STRATEGIES TO KEEP SAFE ACROSS GEOGRAPHIES

Read Next

8 CHEERS FOR B&F PROJECTS THAT ACED BSC’S 5‑STAR RATING!

Leave a Reply

Your email address will not be published. Required fields are marked *

90 − 88 =